Friday, November 26, 2010

Scaffolding and second lot of bricks delivered to site today

Spoke to SS this morning and the Scaffolding was delivered already to the back of the site and he was expecting the second lot of 6,000 bricks to be delivered too. The scaffolding is scheduled to go up on Monday and the Brickies should be back again on Wednesday to start the work..

This great weather hopefully continues during the next couple of weeks for the brick work to complete and the roof to be installed too