Tuesday, October 26, 2010

Work on the Frame Started Today

We have seen activity on the lot this morning with more Frame and Windows delivered

here are some pictures from this morning









Monday, October 25, 2010

Frame delivered on Friday

We had the frame delivered to the lot on Friday (22/10/2010)

Since it has been raining on the weekend the work had not started today ..

Here is hoping the sun stays out the next couple of days for the boys to start work on the lot!!





Thursday, October 21, 2010

Ground Floor Frames to be delivered tomorrow

Contacted the SS today and had a chat about the frames and when the work will start.
He said the Ground floor frames are scheduled to be delivered tomorrow and the First floor frames are planned for delivery on Monday. He also said that the boys should be around to start the work on the frames on Monday (25/10/2010) Fingers crossed the weather stays clear in the next couple of weeks

Wednesday, October 20, 2010

Drainage Pipes and Water Connected

Last Friday the Drainage Pipes were installed and the Water Supply Connected to the Water Mains ..
Some of the Pipes on the Slab seem to be damaged or roughly dealt with instead of being cut with a saw. Had a chat to the SS about the pipes and he said they will be rectified when the requirement arise to work on them. The reason for the damage is due to the lots next to ours already been worked on and fenced and the drainage installers needed to get the machine on the slab etc.. (All under control  phew....)

Here are some pics of the site with a bit more light than last time










Tuesday, October 19, 2010

More Pictures of Slab Curing

We had a lot of rain in the last couple of days and the slab has been curing very nicely with the light weather !! Uncle Hector and my self (Marlon) measured the slab too to ensure the measurements were according to the plans !!

here are some pics on a dull evening...





Uncle Hector checking the Slab


Sunday, October 10, 2010

Slab Poured quicker than expected.. YaY !!

We have been eagerly waiting for this day and the Slab was poured on Friday (08/10/10) earlier than the scheduled day. We think that the workers saw a opportunity due to the good weather on Friday and they went for it..

here are pics of the slab being poured

Thursday, October 7, 2010

Piering and Foam Work

Had to wait through a couple of rainy days however we have movement on the site yesterday with the Piering done and the site being prepared for the Foam and Iron Works for the Slab. Had a quick visit to the site this morning and the Slab dudes were working away and not very talkative at all. Called up the SS and he said if all goes well we should have the slab in by Tuesday (Weather Permitted)

We are very exited to have the slab poured soon so we can get the rest of the build going soon.. :)

Will add some pics here when we get a chance to take some on site tomorrow ..

Friday, October 1, 2010

SS called and Work starting after Long Weekend

We sent an email and had chat to the Wisdom Admin staff yesterday and our SS called to introduce him self a few hours after. He said that they will start working on the site in preparation for the piers and slab on Tuesday (Weather permitting of course) Here is hoping the weather will stay clear for all of us on the long weekend :)