# 2011 March 15 - Stairs to be installed
# 2011 March 11 - Site Locked up
# 2011 March 1o - Internal Linings Completed
# 2011 February 26 - Solar Power Connected to Grid
........ couple of items missing :)
# 2010 December 22 - Brick Work Completed
#2010 November 10 -Plumbing Work Completed
# 2010 November 3 – Frame Work Completed
# 2010 October 26 – Frame Work Started
# 2010 October 22 - Frame Delivered
# 2010 October 15 - Water and Drainage Pipes Installed
# 2010 October 8 - Slab Poured
# 2010 October 6 - Piering and Foam Work Started
# 2010 September 24 - Site Scraped
# 2010 September 8 - Wisdom Sign up on site with green fence
# 2010 September 1 - Signed off Post Tender Variations and End Panel
# 2010 August 31 - Received Construction Certificate
# 2010 August 24 - Site Pegout completed
# 2010 August 12 - Received Council Approval (DA) and have applied for the Construction Certificate
# 2010 June 30 - Submitted plans for Council Approval (DA)
# 2010 June 23 - Received approval notice from Urban Pacific that the plans were approved and ready to send to council for Construction Approvals
# 2010 June 09 - Wisdom submitted the new plans to SCR Review Board (Thanks Sandi for a quick turnaround)
# 2010 June 08 - SCR Design Review Request Redraw Plans and Landscape Design
# 2010 May 28 - Submit Plans to SCR Design Review Board
# 2010 May 23 - Signed the Wisdom Contracts & Colour appointment with Anita