Since it has been raining on the weekend the work had not started today ..
Here is hoping the sun stays out the next couple of days for the boys to start work on the lot!!
# 2011 March 15 - Stairs to be installed
# 2011 March 11 - Site Locked up
# 2011 March 1o - Internal Linings Completed
# 2011 February 26 - Solar Power Connected to Grid
........ couple of items missing :)
# 2010 December 22 - Brick Work Completed
#2010 November 10 -Plumbing Work Completed
# 2010 November 3 – Frame Work Completed
# 2010 October 26 – Frame Work Started
# 2010 October 22 - Frame Delivered
# 2010 October 15 - Water and Drainage Pipes Installed
# 2010 October 8 - Slab Poured
# 2010 October 6 - Piering and Foam Work Started
# 2010 September 24 - Site Scraped
# 2010 September 8 - Wisdom Sign up on site with green fence
# 2010 September 1 - Signed off Post Tender Variations and End Panel
# 2010 August 31 - Received Construction Certificate
# 2010 August 24 - Site Pegout completed
# 2010 August 12 - Received Council Approval (DA) and have applied for the Construction Certificate
# 2010 June 30 - Submitted plans for Council Approval (DA)
# 2010 June 23 - Received approval notice from Urban Pacific that the plans were approved and ready to send to council for Construction Approvals
# 2010 June 09 - Wisdom submitted the new plans to SCR Review Board (Thanks Sandi for a quick turnaround)
# 2010 June 08 - SCR Design Review Request Redraw Plans and Landscape Design
# 2010 May 28 - Submit Plans to SCR Design Review Board
# 2010 May 23 - Signed the Wisdom Contracts & Colour appointment with Anita