Friday, November 26, 2010
Scaffolding and second lot of bricks delivered to site today
Spoke to SS this morning and the Scaffolding was delivered already to the back of the site and he was expecting the second lot of 6,000 bricks to be delivered too. The scaffolding is scheduled to go up on Monday and the Brickies should be back again on Wednesday to start the work..
This great weather hopefully continues during the next couple of weeks for the brick work to complete and the roof to be installed too
This great weather hopefully continues during the next couple of weeks for the brick work to complete and the roof to be installed too
Thursday, November 25, 2010
Bricking continues
We had a slight glitch with the bricks since the Brick that we had chosen have a lot of chips and defects due to transport etc. The reason for this is the smooth face on them is quite brittle around the edges and can easily be damaged. We found that the brickies took extra long time to lay these brick too since they had to check each brick carefully before laying them.. they have discarded quite a few bricks ..
Today we had a meeting with Austral Rep regarding the replacement of the damaged bricks .. they said what ever we need as replacement will be sent to the site on request ..
We are still working out if we are going to pursue the removal of chipped bricks from one of the main walls in the front of the house before the brickies were careful about picking only the good bricks (before we reported the issue to the SS)
here are some pics of the work so far
Today we had a meeting with Austral Rep regarding the replacement of the damaged bricks .. they said what ever we need as replacement will be sent to the site on request ..
We are still working out if we are going to pursue the removal of chipped bricks from one of the main walls in the front of the house before the brickies were careful about picking only the good bricks (before we reported the issue to the SS)
here are some pics of the work so far
Wednesday, November 17, 2010
Bricks / Sand / Cement Delivered to site
The Bricks were delivered to the site on Friday as scheduled and looking at them closer we have noticed quite a few of them have been damaged especially the ones at the back of the property (seems like a couple of pallets have been dropped on delivery)
The Cement and Sand was delivered yesterday and the rain has held any work from proceeding (Ground is too bogged down to work on at the moment)
Here is hoping the rain will stay clear or light enough so the work can start at the site .. Some pictures of the bricks etc
The Cement and Sand was delivered yesterday and the rain has held any work from proceeding (Ground is too bogged down to work on at the moment)
Here is hoping the rain will stay clear or light enough so the work can start at the site .. Some pictures of the bricks etc
Thursday, November 11, 2010
Our Plumbing Work Completed
Yesterday i was driving past in the morning and saw the plumbers at the site .. lucky caught them onsite since they were going to install the garden taps in the wrong places etc..
We have not visited the site and inspected the plumbing in details yet (will have to do this on the weekend because of busy morning work schedule)
Tomorrow (Friday) we are expecting the Austral truck with 12,400 odd feature bricks for our home (not sure how many 1000 standard bricks they will deliver for the Facade rendered area (balcony and portico)
Hope the rain clerars for next week so the brickies can start work.
We have not visited the site and inspected the plumbing in details yet (will have to do this on the weekend because of busy morning work schedule)
Tomorrow (Friday) we are expecting the Austral truck with 12,400 odd feature bricks for our home (not sure how many 1000 standard bricks they will deliver for the Facade rendered area (balcony and portico)
Hope the rain clerars for next week so the brickies can start work.
Saturday, November 6, 2010
from the second floor
Second floor frame went up very quickly (all up the frame was done in 5 working days excluding the rainy days) very efficient and professional team (two blokes)
here are some pictures of the second floor frame and roof trusses ..
Thursday, November 4, 2010
Our Frame Completed
Our Frame is finally completed and the workmanship looks pretty neat and tidy .. the guys who were installing the frame were very professional and tidy. Here are some pictures from this morning (Sorry the sky was overcast..) will take some more pictures of the second floor internals and post in the next couple of days
Tuesday, November 2, 2010
Progress from Yesterday - Second Floor
Today is Melbourne Cup day and don't seem to have much activity at the estate at all ..
The boys were working on the frame yesterday through the rain and these are some pictures from this morning ..
Monday, November 1, 2010
More work on Frame
Here are some pictures taken on the weekend of the progress on the frame. Hope it does not rain through the week for the second floor frame to go up..
Subscribe to:
Posts (Atom)